"Enbridge Inc plans to restart on Tuesday a pipeline that leaked more than 1,000 barrels of crude onto a Wisconsin field after receiving the greenlight from U.S. regulators."
"U.S. pipeline regulators last week issued Enbridge a corrective action order, calling for measures to be taken before it would allow the resumption of flows along Line 14, which was halted after a leak was discovered on July 27.
The Department of Transportation's Pipeline and Hazardous Materials Safety Administration said on Monday that a series of provisions for Enbridge had been met in order to restart the 318,000 barrel-per-day pipeline, which carries Canadian crude to refineries in the Chicago-area."
Ayesha Rascoe, NR Sethuraman, and Soma Das report for Reuters August 6, 2012.