"A proposal to move large amounts of wind and solar power out of the Southwest by linking the three separate North American electricity grids with state-of-the-art switching terminals and superconducting cables is now in hands of federal regulators.
Tres Amigas LLC has petitioned the Federal Energy Regulatory Commission for two key rulings that it says will determine whether the potentially pathbreaking project goes forward. One decision would allow Tres Amigas to charge generators competitive rates rather than cost-based charges to move power over a triangular network of high-voltage direct-current lines it plans to build near Clovis, N.M., 1 mile from the Texas border."
Peter Behr reports for ClimateWire December 23, 2009.
"An Electric 'Game Changer' Gets FERC Scrutiny"
Source: NYTimes, 12/24/2009